Rajiv can do a piece of work in 10 days, Venky in 12 days and Ravi in 15 days.…
TCS · 2024
Rajiv can do a piece of work in 10 days, Venky in 12 days and Ravi in 15 days. They all start the work together, but Rajiv leaves after 2 days and Venky leaves 3 days before the work is completed. In how many days is the work completed?
- A.
5
- B.
6
- C.
9
- D.
7
Attempted by 17 students.