Given a project that uses the COCOMO model with an estimated effort of 2000…
Given a project that uses the COCOMO model with an estimated effort of 2000 person-months and a productivity rate of 5 person-month per KLOC, what is the estimated size of the project in KLOC?
- A.
200
- B.
400
- C.
100
- D.
50