For a software project, following information about the domain characteristics are given:
Sl No | Description | Count | Average Weight factor |
1 | Number of user inputs | 30 | 4 |
2 | Number of user outputs | 60 | 5 |
3 | Number of user enquiries | 20 | 4 |
4 | Number of files | 5 | 10 |
5 | Number of external interfaces | 4 | 7 |
Assume that all complexity adjustment values are average having scale = 3. The function point value for the project will be:
- A.
681.46
- B.
186.46
- C.
816.46
- D.
618.46