PYQ UGC NET 2024
A man and a boy completed a piece of work in 10 days and were paid ₹10,000. The man was 50% more efficient than the boy. What is the difference between their daily wages?
- A.
₹100
- B.
₹500
- C.
₹400
- D.
₹200