Working 9 hours a day, 12 persons complete a work in 25 days. Working 6 hours…
PYQ UGC NET 2024
Working 9 hours a day, 12 persons complete a work in 25 days. Working 6 hours a day, 15 persons can do the same work in:
- A.
28 days
- B.
29 days
- C.
30 days
- D.
32 days
Attempted by 12 students.