Mohan and Sohan can do a piece of work in 18 days. Sohan and Shyam can do the same work in 24 days and Mohan and Shyam can do the same work in 36 days. How long will Mohan, Sohan and Shyam will take to do the work working together ?
- A.
20 days
- B.
18 days
- C.
15 days
- D.
16 days