Mohan can do a piece of work in 7 days working 9 hours a day and Shyam can do…

PYQ UGC NET 2025

Mohan can do a piece of work in 7 days working 9 hours a day and Shyam can do the same work in 6 days working 7 hours a day. How long will they take to complete the job working together and 8258\frac{2}{5} hours a day?

  1. A.

    3 days

  2. B.

    4 days

  3. C.

    3123\frac{1}{2} days

  4. D.

    5 days

Sign up free to check your answer

Sign up free