12 men are assigned a job to be finished in 30 days. After 10 days it is…
PYQ UGC NET 2023
12 men are assigned a job to be finished in 30 days. After 10 days it is observed that only 1/6 of the job is completed. How many extra men are required to be deployed to do the rest of the job so that the job is completed within the scheduled time?
- A.
20
- B.
22
- C.
18
- D.
16