12 men are assigned a job to be finished in 30 days. After 10 days it is…

PYQ UGC NET 2023

12 men are assigned a job to be finished in 30 days. After 10 days it is observed that only 1/6 of the job is completed. How many extra men are required to be deployed to do the rest of the job so that the job is completed within the scheduled time?

  1. A.

    20

  2. B.

    22

  3. C.

    18

  4. D.

    16

Attempted by 10 students.