In a batch system using shortest-job-first scheduling, what is the average…
In a batch system using shortest-job-first scheduling, what is the average turnaround time for a set of four jobs whose running times are 13, 3, 10 and 15 minutes?
- A.
8.33
- B.
20.75
- C.
11.25
- D.
None of the above