Consider three process A, B and C to be scheduled as per SRTF scheduling. The…
Consider three process A, B and C to be scheduled as per SRTF scheduling. The process A known to be scheduled first and when A has run for 7 units C arrives, and when process C has run for 1 unit, process B arrived and completed running for 2 units. Then what could be the minimum burst time of process A and C?
- A.
12,3
- B.
12,4
- C.
11, 3
- D.
11, 4
Attempted by 229 students.
Sign up free to check your answer