A, B and C together can complete 66⅔ % of work in 2 days and A & B together…
PYQ IBPS 2023 (paper not recorded)
A, B and C together can complete 66⅔ % of work in 2 days and A & B together can complete 30% of the work in 3 days. Find the time taken by C alone to complete 4⅔ of total work.
- A.
20 days
- B.
15 days
- C.
7.5 days
- D.
5 days
- E.
12 days
Attempted by 14 students.