An automobile plant contracted to buy shock absorbers from two suppliers X and…

2012

An automobile plant contracted to buy shock absorbers from two suppliers X and Y. X supplies 60% and Y supplies 40% of the shock absorbers. All shock absorbers are subjected to a quality test. The ones that pass the quality test are considered reliable. Of X’s shock absorbers, 96% are reliable. Of Y’s shock absorbers, 72% are reliable.

The probability that a randomly chosen shock absorber, which is found to be reliable, is made by Y is

  1. A.

    0.288

  2. B.

    0.334

  3. C.

    0.667

  4. D.

    0.720

Attempted by 42 students.

Show answer & explanation

Correct answer: B

Probability that the absorber is reliable = 0.96*0.6 + 0.72*0.4

= 0.576 + 0.288

Probability that the absorber is from y and reliable =

(Probability that is made by Y) X (Probability that it is reliable)

= 0.4 * 0.72

= 0.288

The probability that randomly picked reliable absorber is from y =

(Probability that the absorber is from y and reliable) / (>Probability that the absorber is reliable )

= (0.288)/ (0.576 + 0.288)

= 0.334