A can complete a piece of work in 26 days and B can complete it in 16 days. If…
PYQ DSSSB 2025
A can complete a piece of work in 26 days and B can complete it in 16 days. If they work
on alternate days, starting with B on the first day, how long will they take (in days) to
finish the work?