A can complete a certain work in 19 days and B can complete it in 25 days. If they work on alternate days, starting with B on the first day, in how many days will the work be completed?

  1. A.

    2091620\frac{9}{16} days

  2. B.

    20162520\frac{16}{25} days

  3. C.

    21162521\frac{16}{25} days

  4. D.

    2191621\frac{9}{16} days