Consider the following data for a project of 300 days duration. Budgeted Cost…

PYQ GATE 2024

Consider the following data for a project of 300 days duration.

Budgeted Cost of Work Scheduled (BCWS) = Rs. 200

Budgeted Cost of Work Performed (BCWP) = Rs. 150

Actual Cost of Work Performed (ACWP) = Rs. 190

The ‘schedule variance’ for the project is

  1. A.

    (−)Rs. 50

  2. B.

    (−)50 days

  3. C.

    (+)Rs. 50

  4. D.

    (+)50 days