(a) Four jobs are waiting to be run. Their expected run times are 6, 3, 5 and…
PYQ GATE 1998
(a) Four jobs are waiting to be run. Their expected run times are 6, 3, 5 and x. In what order should they be run to minimize the average response time?

(b) Write a concurrent program using par begin-par end to represent the procedure graph shown below.