Match the 5 CMM Maturity levels/CMMI staged representations in List-I with their characterizations in List-II :
(a)(b)(c)(d)(e)List-IInitialRepeatableDefinedManagedOptimizing(i)(ii)(iii)(iv)(v)List-IIProcesses are improved quantitativelyand continually.The plan for a project comes from atemplate for plans.The plan uses processes that can be measured quantitatively.There may not exist a plan or it may be abandoned.There’s a plan and people stick to it.