During the change control process, which of the following activities are…

MH-SET 2021

During the change control process, which of the following activities are required to be initiated ?

(i) While software configuration identification (SCI) is under development it can change freely since it is not under SCM.

(ii) While under review, the software configuration identification (SCI) is considered to be “Frozen”.

(iii) Once SCI is reviewed and approved, it is entered into a library; the SCI is now formally under SCM.

(iv) Check in-check out process : once the change has been approved, the SCI has to be checked out from the library for change; once the change has been implemented, the SCI must be checked in to the library.

  1. A.

    (i), (ii), (iii) and (iv)

  2. B.

    (ii), (iii) and (iv)

  3. C.

    (i), (ii) and (iii)

  4. D.

    (i) and (iv)