A work could be completed by certain workers in 22 days. However, due to 3…

2024

A work could be completed by certain workers in 22 days. However, due to 3 workers being absent, it was completed in 24 days. The original number of workers was –

Answer: C. 36Concept: When a fixed job is done by equally-efficient workers, the total work stays constant and equals the number of workers multiplied by the number of…

  1. A.

    38

  2. B.

    42

  3. C.

    36

  4. D.

    45

Attempted by 115 students.

Show answer & explanation

Correct answer: C

Concept: When a fixed job is done by equally-efficient workers, the total work stays constant and equals the number of workers multiplied by the number of days taken. So for the same job done by two different-sized crews: Workers1 × Days1 = Workers2 × Days2.

  1. Let x be the original number of workers, who complete the job in 22 days.

  2. With 3 workers absent, only (x − 3) workers complete the same job, taking 24 days instead.

  3. Since the total work is the same in both cases, equate workers × days: x × 22 = (x − 3) × 24.

  4. Expand the right-hand side: 22x = 24x − 72.

  5. Collect the x terms on one side: 24x − 22x = 72, so 2x = 72.

  6. Divide both sides by 2: x = 36.

Cross-check: 36 workers × 22 days = 792 units of work. With 3 workers absent, 33 workers × 24 days = 792 units of work — the same total, confirming the original number of workers was 36.