2 men can do a work in 14 days. Then find how many men are required to finish…

2025

2 men can do a work in 14 days. Then find how many men are required to finish the work in 4 days?

Answer: A. 7

  1. A.

    7

  2. B.

    8

  3. C.

    5

  4. D.

    9

Attempted by 1156 students.

Show answer & explanation

Correct answer: A