A man has a job, which requires him to work 8 straight days and rest on the…

2026

A man has a job, which requires him to work 8 straight days and rest on the ninth day. If he started work on Monday, find the day of the week on which he gets his 12th rest day.

Answer: B. WednesdayAnswer: Wednesday Explanation: Rest days occur every 9th day (he works 8 days and rests on the 9th). Therefore the 12th rest day is on day 9 × 12 = 108. To…

  1. A.

    Thursday

  2. B.

    Wednesday

  3. C.

    Tuesday

  4. D.

    Friday

Attempted by 476 students.

Show answer & explanation

Correct answer: B

Answer: Wednesday

Explanation:

  • Rest days occur every 9th day (he works 8 days and rests on the 9th). Therefore the 12th rest day is on day 9 × 12 = 108.

  • To find the weekday, treat day 1 as Monday. Compute (108 − 1) mod 7 = 107 mod 7 = 2.

  • A remainder of 2 means the day is two days after Monday, which is Wednesday.