A work could be completed by certain workers in 22 days. However, due to 3…
TCS · 2024
A work could be completed by certain workers in 22 days. However, due to 3 workers being absent, it was completed in 24 days. The original number of workers was –
- A.
38
- B.
42
- C.
36
- D.
45