B takes 12 more days than A to finish a task. B and A start this task and A…

Infosys · 2023Hexaware · 2025Cognizant · 2023CoCubes · Computer Science · 2025eLitmus · Computer Science · 2024TCS · 2024

B takes 12 more days than A to finish a task. B and A start this task and A leaves the task 12 days before the task is finished. B completes 60% of the overall task. How long would B have taken to finish the task if he had worked independently?

  1. A.

    48 days

  2. B.

    36 days

  3. C.

    28 days

  4. D.

    32 days