An excavation is to be carried out in an ordinary soil for a foundation, which…

PYQ SSC JE (Junior Engineer) 2020

An excavation is to be carried out in an ordinary soil for a foundation, which includes lift of 1.5 m and disposal up to 30 m. The volume of earthwork that can be excavated by a single beldar/majdoor in one day as per Central Public Works Department (CPWD) norms will be roughly equal to:

  1. A.

    5 m^3

  2. B.

    3 m^3

  3. C.

    4 m^3

  4. D.

    2 m^3