Assume that the following jobs are to be executed on a single processor…
PYQ GATE 1993
Assume that the following jobs are to be executed on a single processor system. The jobs are assumed to have arrived at time t = 0⁺ and in the order P, Q, R, S, T; calculate the departure time (completion time) for job P if scheduling is round robin with time slice 1.
Job Id | CPU Burst Time |
|---|---|
P | 4 |
Q | 1 |
R | 8 |
S | 1 |
T | 2 |
- A.
4
- B.
10
- C.
11
- D.
12
- E.
None of the above