System development cost estimation with use-cases is problematic when the…

PYQ UGC NET 2007Modified — slightly modified from the official paper; see the solution

System development cost estimation with use-cases is problematic when the use-case descriptions abstract away costly system behavior. What is the resulting estimation problem?

  1. A.

    of paucity of examples

  2. B.

    the data can be totally incorrect

  3. C.

    the expertise and resource available are not used

  4. D.

    the problem is being over simplified