A system contains 10 units of resource of same type. The resource requirement…

PYQ UGC NET 2013

A system contains 10 units of

resource of same type. The resource

requirement and current allocation of

these resources for three processes P,

Q and R are as follows :

P

Q

R

Maximum requirement

8

7

5

Current allocation

4

1

3

Now, consider the following resource

requests :

(i) P makes a request for 2 resource units.

(ii) Q makes request for 2 resources units.

(iii) R makes a request of 2 resource units.

For a safe state, which of the

following options must be satisfied ?

  1. A.

    Only request (i)

  2. B.

    Only request (ii)

  3. C.

    Only request (iii)

  4. D.

    Request (i) and (ii)