Consider four processes: A, B, C, D are supposed to be scheduled on a system.…

Consider four processes: A, B, C, D are supposed to be scheduled on a system. All process are arrived at time zero and burst time equals to 6, 3, 5 and 1 nanoseconds respectively. Let P be the process which finishes second last when round robin scheduling is used with time quantum 2ns and Q be the process which finishes third last when round robin scheduling is used with time quantum 4ns. Then P and Q are ?

  1. A.

    B, C

  2. B.

    C, D

  3. C.

    A, D

  4. D.

    C, А