A can complete a task in 12 days. B can complete the task in 18 days. If A and…
PYQ Infosys Hiring Test 2024
A can complete a task in 12 days. B can complete the task in 18 days. If A and B work on this same task in alternate days starting with A, in how many days do they finish the entire task?
- A.
10.8 days
- B.
14.33 days
- C.
11 days
- D.
8.4 days
Attempted by 47 students.
Sign up free to check your answer