PYQ IBPS SO CRP SPL-XIII (2023)

Consider the following processes, all arriving at time 0, with their respective burst times:

Process

Burst Time (ms)

P1

6

P2

8

P3

7

P4

3

Using Non-Preemptive Shortest Job First (SJF) scheduling, calculate the average waiting time.

  1. A.

    7.0 ms

  2. B.

    5.5 ms

  3. C.

    6.25 ms

  4. D.

    5.0 ms

  5. E.

    6.0 ms

Attempted by 47 students.