Consider the following processes with their respective burst times and arrival…

PYQ IBPS SO CRP SPL-XII (2022)

Consider the following processes with their respective burst times and arrival times:

Process

Arrival Time

Burst Time

P1

0

5

P2

2

3

P3

4

1

P4

6

8

P5

8

6

Using the First-Come, First-Served (FCFS) scheduling algorithm, calculate the average waiting time and average turnaround time for the processes.

  1. A.

    Average Waiting Time: 4.2, Average Turnaround Time: 8.2

  2. B.

    Average Waiting Time: 6.0, Average Turnaround Time: 11.0

  3. C.

    Average Waiting Time: 4.6, Average Turnaround Time: 8.6

  4. D.

    Average Waiting Time: 3.8, Average Turnaround Time: 8.4

  5. E.

    Average Waiting Time: 3.6, Average Turnaround Time: 7.6

Attempted by 42 students.