A, B, and C together can complete a piece of work in 10 days, and B and C…
PYQ IBPS Clerk CRP CSA-XV (2025)
A, B, and C together can complete a piece of work in 10 days, and B and C together can do the same work in 25 days. Find the time taken by A alone to complete the work (in days).
- A.
6.67
- B.
8.33
- C.
12.5
- D.
13.33
- E.
16.67