Which of the following statement(s) is/are true regarding PERT chart in software project management? I. PERT charts consists of a network of boxes and arrows. II. In PERT chart, the boxes represent activities and the arrow represents task dependencies.
- A.
Only I
- B.
Only II
- C.
Both I and II
- D.
Neither I nor II